SCHEDULE UPDATE
Water Service Transfers: Phases 1 & 2 are complete; about 100 Phase 3 transfers remain, on track for end of May completion.
Yard Restoration: As connections wrap up, topsoil arrives by June, followed by hydroseeding.
Paving: Planned for Fall 2025, but may begin this summer if progress and weather permit. A detailed schedule will be shared soon.